Reconstruction of Oakridge Road
Federal contribution
$113,098
Federal share33%
of $339.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of McDougall
- Construction start
- Jul 19, 2009(actual)
- Construction end
- Nov 30, 2009(actual)
Also in Nobel