Back to projects

Improvements to Snug Harbour Rd.

Nobel, Ontario

completeHighways and RoadsCC
Federal contribution
$91,667
Federal share33%

of $275.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Township of Carling
Construction start
Jun 29, 2009(actual)
Construction end
Aug 28, 2009(actual)

Also in Nobel

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23945 in the federal list. How to read these figures.