Back to projects

Improvements to East and West Carling Bay Road and Bayview Drive

Nobel, Ontario

completeHighways and RoadsCC Top Up
Federal contribution
$776,585
Federal share33%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Township of Carling
Construction start
Apr 22, 2010(actual)
Construction end
Sep 30, 2010(actual)

Against the original forecast

  • Construction end3 months earlyforecast Dec 31, 2010

Also in Nobel