Back to projects

Killbear Road Rehabilitation

Nobel, Ontario

completeHighways and RoadsISF
Federal contribution
$350,000
Federal share50%

of $700.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 12, 2010
2011
Built

Approved 6 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Ontario
Construction start
May 17, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Jun 1, 2010

Also in Nobel

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39687 in the federal list. How to read these figures.