Replacement of River Mill Line Bridge
Federal contribution
$102,300
Federal share33%
of $306.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Ashfield-Colborne-Wawanosh
- Construction start
- Aug 3, 2009(actual)
- Construction end
- Nov 30, 2009(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Dec 31, 2009