Back to projects

Upgrade of the Hawkesbury Wastewater Treatment Plant

Hawkesbury, Ontario

completeWastewaterCC
Federal contribution
$11.9M
$11,859,955
Federal share33%

of $35.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
200920102011201220132014
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Hawkesbury
Construction start
Aug 23, 2010(actual)
Construction end
Feb 21, 2014(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast Oct 4, 2010
  • Construction end6 weeks lateforecast Jan 10, 2014

Also in Hawkesbury

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24631 in the federal list. How to read these figures.