Upgrade of the Hawkesbury Wastewater Treatment Plant
Federal contribution
$11.9M
$11,859,955
Federal share33%
of $35.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
200920102011201220132014
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Hawkesbury
- Construction start
- Aug 23, 2010(actual)
- Construction end
- Feb 21, 2014(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Oct 4, 2010
- Construction end6 weeks lateforecast Jan 10, 2014
Also in Hawkesbury
- Hawkesbury Water Treatment Plant Clarifier Upgrades$1.1M
- Replacement of 550 meters of water main with new 200mm conduit and replacement of all lateral services$550.0K
- Installation of a 250mm diameter water main on Bon Pasteur Street between McGill Street and Geneviève Street$287.5K
- Robert Hartley Sports Complex COVID Improvements$140.0K
- Upgrading of 350 meters of the Tessier Street ditch located between 1250 Tessier St to 900 Tupper St and replacement of 59 meters of undersized culverts with 89 meters of elliptical concrete culverts.$112.2K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24631 in the federal list. How to read these figures.