Replacement of 550 meters of water main with new 200mm conduit and replacement of all lateral services

Hawkesbury, Ontario

completeDrinking WaterCWWF
Federal contribution
$550,000
Federal share50%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Hawkesbury
Construction start
Jun 6, 2017(actual)
Construction end
Jul 17, 2019(actual)

Against the original forecast

  • Construction end3 weeks lateforecast Jun 28, 2019

Also in Hawkesbury

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50127 in the federal list. How to read these figures.