Back to projects

Upgrading of 350 meters of the Tessier Street ditch located between 1250 Tessier St to 900 Tupper St and replacement of 59 meters of undersized culverts with 89 meters of elliptical concrete culverts.

Hawkesbury, Ontario

completeWastewaterCWWF
Federal contribution
$112,158
Federal share45%

of $250.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Hawkesbury
Construction start
Nov 20, 2017(actual)
Construction end
Jan 7, 2020(actual)

Against the original forecast

  • Construction start4 months lateforecast Jul 17, 2017
  • Construction end2 months lateforecast Oct 25, 2019

Also in Hawkesbury