Upgrading of Ena Lake Road

Kenora, Ontario

completeHighways and RoadsCC
Federal contribution
$17,550
Federal share45%

of $39.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Construction start
Oct 5, 2009(actual)
Construction end
Sep 24, 2010(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2009

Also in Kenora

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24713 in the federal list. How to read these figures.