Back to projects

Retrofitting the St. Martin Catholic School into the Terrace Bay Public Library

Terrace Bay, Ontario

completeCultureCC
Federal contribution
$622,520
Federal share33%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Township of Terrace Bay
Construction start
Aug 4, 2009(actual)
Construction end
Aug 31, 2010(actual)

Against the original forecast

  • Construction start8 weeks earlyforecast Oct 1, 2009
  • Construction end4 weeks lateforecast Jul 31, 2010

Also in Terrace Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24720 in the federal list. How to read these figures.