Reconstruction of Mill Road

Terrace Bay, Ontario

completeHighways and RoadsRNIS
Federal contribution
$889,594
Federal share59%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 15, 2020
20212022
Built

Approved 4 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Township of Terrace Bay
Construction start
May 1, 2020(actual)
Construction end
Sep 2, 2022(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Mar 27, 2020
  • Construction end8 months lateforecast Dec 31, 2021