Reconstruction of Mill Road
Federal contribution
$889,594
Federal share59%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 15, 2020
20212022
Built
Approved 4 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Township of Terrace Bay
- Construction start
- May 1, 2020(actual)
- Construction end
- Sep 2, 2022(actual)
Against the original forecast
- Construction start5 weeks lateforecast Mar 27, 2020
- Construction end8 months lateforecast Dec 31, 2021
Also in Terrace Bay
- Ventilation System Upgrade; Ultra Violet Germicidal Irradiation System; Water Bottle Filling Station$1.3M
- Kenogami Road Reconstruction Phase II$919.8K
- Retrofitting the St. Martin Catholic School into the Terrace Bay Public Library$622.5K
- Replacement of Lakeview Dr. & Kenogami Rd. Sanitary Sewage Outfall$166.1K
- Neys Visitor Centre Improvements$100.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54580 in the federal list. How to read these figures.