Neys Visitor Centre Improvements
Federal contribution
$100,000
Federal share50%
of $200.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 12, 2010
2011
Built
Approved 6 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Ontario
- Construction start
- Sep 20, 2010(actual)
- Construction end
- Mar 25, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Sep 1, 2010
Also in Terrace Bay
- Ventilation System Upgrade; Ultra Violet Germicidal Irradiation System; Water Bottle Filling Station$1.3M
- Kenogami Road Reconstruction Phase II$919.8K
- Reconstruction of Mill Road$889.6K
- Retrofitting the St. Martin Catholic School into the Terrace Bay Public Library$622.5K
- Replacement of Lakeview Dr. & Kenogami Rd. Sanitary Sewage Outfall$166.1K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39700 in the federal list. How to read these figures.