Kenogami Road Reconstruction Phase II
Federal contribution
$919,800
Federal share40%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2021
Built
Approved 7 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Township of Terrace Bay
- Construction start
- May 17, 2021(actual)
- Construction end
- Aug 31, 2021(actual)
Against the original forecast
- Construction end2.4 years earlyforecast Jan 31, 2024
Also in Terrace Bay
- Ventilation System Upgrade; Ultra Violet Germicidal Irradiation System; Water Bottle Filling Station$1.3M
- Reconstruction of Mill Road$889.6K
- Retrofitting the St. Martin Catholic School into the Terrace Bay Public Library$622.5K
- Replacement of Lakeview Dr. & Kenogami Rd. Sanitary Sewage Outfall$166.1K
- Neys Visitor Centre Improvements$100.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57277 in the federal list. How to read these figures.