Rehabilitation of Government Road Bridge
Federal contribution
$350,000
Federal share33%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Thessalon
- Construction start
- Jul 22, 2010(actual)
- Construction end
- Dec 15, 2010(actual)
Against the original forecast
- Construction start12 months lateforecast Jul 22, 2009
- Construction end7 months lateforecast May 31, 2010
Also in Thessalon
- The Town of Thessalon Sustainability Initiative: Enhancing Energy Efficiency and Accessibility at the Thessalon Memorial Arena and Thessalon Curling Club$2.0M
- Reconstruction of Lakeside Drive$1.7M
- Rehabilitation of Huron Street Watermain$766.4K
- Thessalon River Bridge Rehabilitation$220.2K
- River Street Storm Sewer Rehabilitation$59.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24729 in the federal list. How to read these figures.