Reconstruction of Lakeside Drive
Federal contribution
$1.7M
$1,687,500
Federal share60%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 25, 2020
202120222023
Built
Approved 8 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Thessalon
- Construction start
- Sep 14, 2020(actual)
- Construction end
- Oct 29, 2023(actual)
Also in Thessalon
- The Town of Thessalon Sustainability Initiative: Enhancing Energy Efficiency and Accessibility at the Thessalon Memorial Arena and Thessalon Curling Club$2.0M
- Rehabilitation of Huron Street Watermain$766.4K
- Rehabilitation of Government Road Bridge$350.0K
- Thessalon River Bridge Rehabilitation$220.2K
- River Street Storm Sewer Rehabilitation$59.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54638 in the federal list. How to read these figures.