River Street Storm Sewer Rehabilitation
Federal contribution
$59,349
Federal share49%
of $120.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Thessalon
- Construction start
- Jul 15, 2017(actual)
- Construction end
- Dec 31, 2018(actual)
Against the original forecast
- Construction start3 months lateforecast Apr 1, 2017
- Construction end12 months lateforecast Dec 31, 2017
Also in Thessalon
- The Town of Thessalon Sustainability Initiative: Enhancing Energy Efficiency and Accessibility at the Thessalon Memorial Arena and Thessalon Curling Club$2.0M
- Reconstruction of Lakeside Drive$1.7M
- Rehabilitation of Huron Street Watermain$766.4K
- Rehabilitation of Government Road Bridge$350.0K
- Thessalon River Bridge Rehabilitation$220.2K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48944 in the federal list. How to read these figures.