Rehabilitation of Huron Street Watermain

Thessalon, Ontario

completeDrinking WaterGIS
Federal contribution
$766,360
Federal share40%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
20232024
Built

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Thessalon
Construction start
May 1, 2024(actual)
Construction end
Sep 20, 2024(actual)

Against the original forecast

  • Construction end14 months earlyforecast Nov 28, 2025