Back to projects

Renovation to Office Building

Foleyet, Ontario

completeGreen EnergyCC
Federal contribution
$33,000
Federal share43%

of $76.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Construction start
May 3, 2010(actual)
Construction end
Jul 22, 2010(actual)

Also in Foleyet