Nat River Bridge Coating
Federal contribution
$163,065
Federal share41%
of $400.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 7, 2010
Built
Approved 2 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Ontario
- Construction start
- Jul 12, 2010(actual)
- Construction end
- Sep 17, 2010(actual)