Rehabilitation of Finn Hill Road
Federal contribution
$26,430
Federal share45%
of $58.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Local Roads Board of Foleyet
- Construction start
- Sep 27, 2010(actual)
- Construction end
- Oct 30, 2010(actual)