Foleyet Community Hall Renovations
Federal contribution
$16,417
Federal share33%
of $49.3K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Foleyet Local Service Board
- Construction start
- Apr 8, 2010(actual)
- Construction end
- May 7, 2010(actual)
Against the original forecast
- Construction start3 months earlyforecast Jul 1, 2010
- Construction end11 months earlyforecast Mar 31, 2011
Also in Foleyet
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32663 in the federal list. How to read these figures.