Bragg Creek Potable Water Treatment Plant & Intake

Rocky View County, Alberta

completeDrinking WaterCC Top Up
Federal contribution
$1.4M
$1,370,033
Federal share32%

of $4.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 21, 2009
201020112012
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Jul 18, 2009(actual)
Construction end
Dec 31, 2011(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 1, 2009
  • Construction end4 months lateforecast Aug 31, 2011