Springbank Off-Stream Reservoir (SR1)
Federal contribution
$168.5M
$168,500,000
Federal share50%
of $337.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 13, 2019
2019202120232025
Built
- Program
- Disaster Mitigation and Adaptation Fund
- Ultimate recipient
- Alberta Ministry of Transportation
- Construction start
- Feb 8, 2022(actual)
- Construction end
- Apr 30, 2025(actual)
Against the original forecast
- Construction start2.3 years lateforecast Oct 31, 2019
- Construction end5 months earlyforecast Oct 1, 2025
Also in Rocky View County