Bragg Creek Potable Water Distribution System

Rocky View County, Alberta

completeDrinking WaterCC
Federal contribution
$1.0M
$1,000,000
Federal share33%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2013201420152016
Built

Approved 3.7 years before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
Oct 31, 2012(actual)
Construction end
Sep 29, 2014(actual)

Against the original forecast

  • Construction start7 months earlyforecast Jun 1, 2013
  • Construction end6 months lateforecast Mar 31, 2014

Also in Rocky View County

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25455 in the federal list. How to read these figures.