Bragg Creek Potable Water Distribution System
Federal contribution
$1.0M
$1,000,000
Federal share33%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2013201420152016
Built
Approved 3.7 years before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipal District of Rocky View No. 44
- Construction start
- Oct 31, 2012(actual)
- Construction end
- Sep 29, 2014(actual)
Against the original forecast
- Construction start7 months earlyforecast Jun 1, 2013
- Construction end6 months lateforecast Mar 31, 2014
Also in Rocky View County
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25455 in the federal list. How to read these figures.