Back to projects

Highway 9

Rocky View County, Alberta

completeHighways and RoadsISF
Federal contribution
$5.0M
$4,984,947
Federal share29%

of $17.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 20, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 7 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
May 25, 2010(actual)
Construction end
Nov 10, 2011(actual)

Also in Rocky View County

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39562 in the federal list. How to read these figures.