Back to projects

Connectivity Infrastructure.....A Connected Grande Prairie

Grande Prairie, Alberta

completeBroadband And ConnectivityCC
Federal contribution
$1.8M
$1,767,363
Federal share33%

of $5.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2010
20102011201220132014
Built

Approved 4 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Grande Prairie
Construction start
Nov 18, 2011(actual)
Construction end
Mar 31, 2014(actual)

Against the original forecast

  • Construction start24 months lateforecast Nov 23, 2009
  • Construction end2.2 years lateforecast Jan 9, 2012

Also in Grande Prairie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25518 in the federal list. How to read these figures.