Quesnel - West Quesnel Land Stability
Federal contribution
$1.6M
$1,577,000
Federal share33%
of $4.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
201020112012201320142015
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Quesnel
- Construction start
- Mar 1, 2012(actual)
- Construction end
- Mar 31, 2015(actual)
Against the original forecast
- Construction start2 months lateforecast Jan 1, 2012
Also in Quesnel
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25689 in the federal list. How to read these figures.