Highway 97 - Cody Road to Australian

Quesnel, British Columbia

completeHighways and RoadsISF
Federal contribution
$2.6M
$2,646,578
Federal share45%

of $5.9M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 7, 2009
ApprovedJan 25, 2010
2010
Built

Approved 10 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
May 4, 2010(actual)
Construction end
Oct 8, 2010(actual)

Against the original forecast

  • Construction end3 weeks earlyforecast Oct 31, 2010

Also in Quesnel

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28987 in the federal list. How to read these figures.