Drinking Water Supply and Storage Upgrades

Quesnel, British Columbia

completeDrinking WaterCWWF
Federal contribution
$1.8M
$1,804,450
Federal share50%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Quesnel
Construction start
Aug 15, 2017(actual)
Construction end
Feb 28, 2020(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jul 24, 2017
  • Construction end5 weeks earlyforecast Mar 31, 2020