West Quesnel Land Stability - Phase 2
Federal contribution
$2.4M
$2,425,051
Federal share33%
of $7.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
20162017
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Quesnel
- Construction start
- May 13, 2016(actual)
- Construction end
- Oct 31, 2017(actual)
Against the original forecast
- Construction end2 months lateforecast Aug 31, 2017