West Quesnel Land Stability - Phase 2

Quesnel, British Columbia

completeWastewaterSCF
Federal contribution
$2.4M
$2,425,051
Federal share33%

of $7.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
20162017
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Quesnel
Construction start
May 13, 2016(actual)
Construction end
Oct 31, 2017(actual)

Against the original forecast

  • Construction end2 months lateforecast Aug 31, 2017