Central-East/South-East Region Water Servicing

Stettler, Alberta

completeDrinking WaterCC
Federal contribution
$3.0M
$3,000,000
Federal share33%

of $9.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 21, 2009
2010201120122013
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
County of Stettler No. 6
Construction start
Apr 1, 2010(actual)
Construction end
Jul 15, 2013(actual)

Against the original forecast

  • Construction start8 months lateforecast Aug 15, 2009
  • Construction end22 months lateforecast Sep 3, 2011