Resurfacing of Highway 12 - Town of Stettler (Various Locations)

Stettler, Alberta

completeHighways and RoadsISF
Federal contribution
$485,500
Federal share50%

of $971.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 24, 2009
ApprovedJul 23, 2010
2010
Built

Approved 10 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Jul 6, 2010(actual)
Construction end
Sep 9, 2010(actual)

Against the original forecast

  • Construction end7 months earlyforecast Mar 31, 2011