Back to projects

Wastewater Treatment Facility Upgrades

Stettler, Alberta

completeWastewaterISF
Federal contribution
$689,847
Federal share33%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010201220142016
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Stettler
Construction start
Aug 23, 2010(actual)
Construction end
Feb 11, 2016(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 15, 2010

Also in Stettler

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28897 in the federal list. How to read these figures.