Stettler Resource Road
Federal contribution
$1.0M
$1,034,742
Federal share33%
of $3.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 21, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- County of Stettler No. 6
- Construction start
- Aug 17, 2009(actual)
- Construction end
- Oct 28, 2010(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jun 24, 2009
- Construction end12 months lateforecast Oct 31, 2009
Also in Stettler
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 25919 in the federal list. How to read these figures.