Water Supply Upgrading - Phase 3

Baie Verte, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$434,230
Federal share33%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.5 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Baie Verte
Construction start
Sep 29, 2009(actual)
Construction end
Mar 30, 2012(actual)

Against the original forecast

  • Construction end22 months lateforecast May 31, 2010