Pump house and Water Intake Upgrades

Baie Verte, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$100,215
Federal share40%

of $250.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 25, 2021
202120222023
Built

Approved 11 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Oct 31, 2022(actual)
Construction end
Oct 27, 2023(actual)

Against the original forecast

  • Construction start6 months lateforecast May 15, 2022
  • Construction end3 weeks earlyforecast Nov 20, 2023