Terra Nova Road Lift Station Upgrades
Baie Verte, Newfoundland and Labrador
Federal contribution
$143,105
Federal share40%
of $357.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
2022202320242025
Built
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Baie Verte
- Construction start
- Aug 15, 2024(actual)
- Construction end
- May 26, 2025(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 15, 2024
- Construction end6 months lateforecast Dec 2, 2024
Also in Baie Verte
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61115 in the federal list. How to read these figures.