Back to projects

Regional Community Centre Retrofit

Baie Verte, Newfoundland and Labrador

underwayRecreationCCRIS
Federal contribution
$1.4M
$1,399,674
Federal share33%

of $4.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
today
2020202220242026
BuiltForecast

Approved 4 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Town of Baie Verte
Construction start
Oct 21, 2021(actual)
Construction end
Dec 31, 2026(forecast)

Against the original forecast

  • Construction start5 months earlyforecast Apr 1, 2022

Also in Baie Verte

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53830 in the federal list. How to read these figures.