Hamlets of Benalto and Lousana Wastewater Storage and Treatment Upgrades
Federal contribution
$838,169
Federal share33%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 21, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- County of Red Deer
- Construction start
- May 1, 2010(actual)
- Construction end
- Mar 2, 2011(actual)
Against the original forecast
- Construction start7 months lateforecast Sep 15, 2009
- Construction end17 months lateforecast Sep 30, 2009