Fort Nelson - Recreation Complex Construction

Fort Nelson, British Columbia

completeRecreationCC Top Up
Federal contribution
$5.0M
$5,000,000
Federal share14%

of $34.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Jan 6, 2010(actual)
Construction end
Jun 16, 2011(actual)

Against the original forecast

  • Construction start3 months lateforecast Oct 1, 2009
  • Construction end5 months earlyforecast Oct 31, 2011