Raw Water Supply Energy Efficiency Upgrades

Fort Nelson, British Columbia

completeDrinking WaterISF
Federal contribution
$200,000
Federal share24%

of $842.8K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedSep 1, 2009
20102011
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
May 1, 2010(actual)
Construction end
Oct 30, 2011(actual)

Against the original forecast

  • Construction start10 months lateforecast Jul 1, 2009
  • Construction end4 weeks lateforecast Sep 30, 2011