Fort Nelson - Drinking Water Quality, Security of Supply and Energy Efficiency

Fort Nelson, British Columbia

completeDrinking WaterISF
Federal contribution
$1.3M
$1,290,000
Federal share33%

of $3.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
May 1, 2010(actual)
Construction end
Jul 20, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Mar 31, 2010
  • Construction end2 months earlyforecast Sep 30, 2011

Also in Fort Nelson

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39157 in the federal list. How to read these figures.