Fort Nelson - Drinking Water Quality, Security of Supply and Energy Efficiency
Federal contribution
$1.3M
$1,290,000
Federal share33%
of $3.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
20102011
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Northern Rockies
- Construction start
- May 1, 2010(actual)
- Construction end
- Jul 20, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Mar 31, 2010
- Construction end2 months earlyforecast Sep 30, 2011