Fort Nelson Community Trail Master Plan

Fort Nelson, British Columbia

completeActive TransportationISF
Federal contribution
$301,338
Federal share25%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedAug 10, 2009
2010
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jul 9, 2009(actual)
Construction end
Aug 31, 2010(actual)

Against the original forecast

  • Construction end5 months lateforecast Mar 31, 2010