Fort Nelson Community Trail Master Plan
Federal contribution
$301,338
Federal share25%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedAug 10, 2009
2010
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Northern Rockies
- Construction start
- Jul 9, 2009(actual)
- Construction end
- Aug 31, 2010(actual)
Against the original forecast
- Construction end5 months lateforecast Mar 31, 2010