Water reservoir expansion & WTP upgrade - Phase 2
Federal contribution
$455,568
Federal share33%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
201020112012
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Duck Lake
- Construction start
- Oct 8, 2009(actual)
- Construction end
- Nov 30, 2011(actual)
Against the original forecast
- Construction start4 months lateforecast Jun 22, 2009
- Construction end4 weeks earlyforecast Dec 31, 2011
Also in Duck Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26637 in the federal list. How to read these figures.