New Wastewater Force Main and Sewage Pumping Station Upgrades
Federal contribution
$345,757
Federal share50%
of $691.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
201820192020
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Duck Lake
- Construction start
- Dec 21, 2017(actual)
- Construction end
- May 5, 2020(actual)
Against the original forecast
- Construction start2 months lateforecast Oct 20, 2017
- Construction end5 weeks lateforecast Mar 31, 2020
Also in Duck Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50019 in the federal list. How to read these figures.