Town of Duck Lake - Community Park Upgrade/Expansion
Federal contribution
$84,365
Federal share40%
of $210.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 6, 2021
20222023
Built
Approved 6 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Duck Lake
- Construction start
- Oct 1, 2022(actual)
- Construction end
- Sep 1, 2023(actual)
Against the original forecast
- Construction start7 months lateforecast Mar 1, 2022