Town of Duck Lake Belladrome Upgrade
Federal contribution
$79,484
Federal share40%
of $198.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 9, 2021
2022
Built
Approved 5 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Duck Lake
- Construction start
- Aug 10, 2021(actual)
- Construction end
- Nov 7, 2022(actual)
Against the original forecast
- Construction start14 months lateforecast Jun 1, 2020
Also in Duck Lake
- Water reservoir expansion & WTP upgrade - Phase 2$455.6K
- New Wastewater Force Main and Sewage Pumping Station Upgrades$345.8K
- Phase 1 - Water Supply and Reservoir Expansion$250.0K
- Town of Duck Lake - Community Park Upgrade/Expansion$84.4K
- Town of Duck Lake Landfill Closure and Decommissioning Planning$82.2K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57383 in the federal list. How to read these figures.