Back to projects

Water System - Phase 1

Lark Harbour, Newfoundland and Labrador

completeDrinking WaterCC
Federal contribution
$455,518
Federal share32%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
2010201120122013
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Lark Harbour
Construction start
May 22, 2012(actual)
Construction end
Dec 1, 2012(actual)

Against the original forecast

  • Construction start23 months lateforecast Jun 30, 2010
  • Construction end2 years lateforecast Nov 30, 2010

Also in Lark Harbour

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26661 in the federal list. How to read these figures.