Water System - Phase 1
Lark Harbour, Newfoundland and Labrador
Federal contribution
$455,518
Federal share32%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 14, 2009
2010201120122013
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Lark Harbour
- Construction start
- May 22, 2012(actual)
- Construction end
- Dec 1, 2012(actual)
Against the original forecast
- Construction start23 months lateforecast Jun 30, 2010
- Construction end2 years lateforecast Nov 30, 2010
Also in Lark Harbour
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26661 in the federal list. How to read these figures.