Back to projects

Proposed Water and Sewer, Phase 4

Lark Harbour, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$438,997
Federal share32%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 10, 2018
20192020
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Lark Harbour
Construction start
Jul 30, 2019(actual)
Construction end
Sep 21, 2020(actual)

Against the original forecast

  • Construction start13 months lateforecast Jul 6, 2018
  • Construction end8 weeks earlyforecast Nov 15, 2020

Also in Lark Harbour

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52224 in the federal list. How to read these figures.