Water and Sewer, Phase 2 & 3

Lark Harbour, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$878,922
Federal share30%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 19, 2016
20172018
Built

Approved 4 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Lark Harbour
Construction start
Aug 5, 2017(actual)
Construction end
Oct 18, 2018(actual)

Against the original forecast

  • Construction start9 months earlyforecast May 15, 2018
  • Construction end5 months earlyforecast Mar 31, 2019